The project will be
implemented during an 18-month period. The project officially
began on 17 November 2008. The draft timeline is as follows:
- 2008 -
November: Draft the research methodology; plan SC meeting December: Draft the research methodology; plan SC
meeting
- 2009 -
January:
SC meeting; finalise research methodology February:
Finalise research methodology; Record, compile and analyse data
March:
Record, compile and analyse data (15 interviews due from each
partner) April:
Record, compile and analyse data May:
Record, compile and analyse data June:
Record, compile and analyse data (25 interviews due from each
partner) July:
Record, compile and analyse data (All interviews due) August:
Produce national reports; produce European comparative report September:
Produce national reports; produce European comparative report October:
Produce national reports; produce European comparative report November:
Produce national reports; produce European comparative report;
Plan final conference December:
SC meeting; review
research; edit and publish final report; discuss final report
recommendations; plan final conference
- 2010 -
January:
Edit and publish final report; plan final conference February:
Edit and publish final
report; plan final conference; Design policy strategy March:
Finish planning final conference; hold final conference; final
SC meeting; design policy strategy; media activities; external
evaluation April:
Media activities; external
evaluation
An internal evaluation process will occur throughout the 18
months of the project.