                                                 Project Timeline

The project will be implemented during an 18-month period.  The project officially began on 17 November 2008.  The draft timeline is as follows:

- 2008 -

November:
  Draft the research methodology; plan SC meeting
December:  Draft the research methodology; plan SC meeting

- 2009 -

January: SC meeting; finalise research methodology
February: Finalise research methodology; Record, compile and analyse data
March: Record, compile and analyse data (15 interviews due from each partner)
April: Record, compile and analyse data
May: Record, compile and analyse data
June: Record, compile and analyse data (25 interviews due from each partner)
July: Record, compile and analyse data (All interviews due)
August: Produce national reports; produce European comparative report
September: Produce national reports; produce European comparative report
October: Produce national reports; produce European comparative report
November: Produce national reports; produce European comparative report; Plan final conference
December: SC meeting; review research; edit and publish final report; discuss final report recommendations; plan final conference
 - 2010 -

January: Edit and publish final report; plan final conference
February: Edit and publish final report; plan final conference; Design policy strategy
March: Finish planning final conference; hold final conference; final SC meeting; design policy strategy; media activities; external evaluation
April: Media activities; external evaluation



An internal evaluation process will occur throughout the 18 months of the project.

 

 
   













 


 
 